Electrical Overhead Crane Revamping.

A significant project where we carried out a complete revamping of the overhead crane automation system, supplying and installing a complete electrical panel. We transitioned from the old slip-ring technology to a new one with motors powered by inverters. This complex work was completed in just 2 weeks, adhering to the plant shutdown schedule without delays. We coordinated the disassembly of the old panels, the assembly of the new ones, and the installation of an on-board machine system and a magnet system, both installed with the assistance of a crane. Successfully completed with testing and validation, ensuring optimal operation of the system. The use of cutting-edge technologies, including Siemens S7-1500 PLC, ABB ACS880 inverter, and supervision through Siemens WinCC, highlights our expertise in managing complex industrial projects.