Asonext Power Center.

The project involved the supply and installation of a new power center at the Asoforge factory (ASONEXT) as part of a structural renewal.

Our team successfully managed the installation of the power center, including laying 100 meters of aluminum power cables, with the installation of cable trays for a total length of 90 meters.

This power center, equipped with 1600A ABB Emax switches, was essential for powering the maintenance warehouse of a company specialized in forging production.

Additionally, we ensured efficient connection with the photovoltaic system installed on the new warehouse, with a capacity of 500 kW.